Secured Vestibules Start June 2012
Create a secured entrance into schools, where feasible, directing visitors through the main office.
Security Upgrades Start June 2012
Includes additional cameras and access controlled doors.
HVAC Upgrades Start June 2012
Replace all mechanical units over 18 years of age at 16 campuses
Hallway Floor Covering Replacement Start June 2012
Replace carpeted hallways with Vinyl Composition Tile
C.B. Watson Primary Start June 2012 - Complete August 2013
New Primary school to be located at 401 Dover Drive in Warner Robins. Includes demolition of existing school. Capacity: 600 students
Linwood Elementary Renovation Start June 2013 - Complete August 2014
Complete and total renovation of existing school. Building to be renamed Pearl Stephens Elementary.
Rumble Academy - Demolition / Green Space Start June 2014
Demolition of Rumble campus excluding gym and new classroom wing. Create green space and renovate classroom wing
Northside High - Tabor Demolition & Addition
Demolition of existing Tabor Campus excluding gym and new classroom wing. Construct classroom addition with administration area, lunchroom & kitchen
Central Bus Facility
Construct central bus facility to serve all county buses and personnel. Location to be determined.
Elementary #11 - Perry Primary Replacement
New Elementary school to be constructed on Langston Road. Capacity: 750 students
Houston County High School Renovation
Complete renovation of original building constructed in 1991
Gym Upgrades
Install sports flooring, lighting, and finishes to include acoustical treatments.
New Sports Facility
Construct stadium and tournament tennis facility on property located at Bear Drive and Cohen Walker Drive in Warner Robins.
McConnell-Talbert Stadium Renovation
Storm water upgrades, lighting upgrades, and facility upgrades including restrooms.
|